Schedule of Activities and Key Milestones

Key dates are as follows:

Milestone Date Key WPs
Start of project 1st July 2013 WP1,2,3,4,7 and 8 begin
Kick off meeting September 2013  
Start Conference September 2013 (October)  
Close of Phase 1 (deliverable) 1st January 2014 WP1,2,3,4
Case studies launched 1st January 2014 WP5
Learning Journey launched 1st July 2014 WP6
Close of Phase 2 (deliverable) 1st January 2015 WP1,2,3,4,5
Interim Conference March 2015  
Final Deliverables/td> 1st March 2016 WP1,2,3,4
Final Conference May 2016  
Close of project 30th June 2016  